Oregon regulators make new data centers in Pacific Power territory pay their own way, as Salem votes on Verrus


Quick Read
The Oregon Public Utility Commission on Friday, Nov. 13, approved Pacific Power's rules for new data centers that use or can use 20 megawatts or more. The rules take effect Jan. 1, 2027.
New data centers must sign contracts of 10 to 30 years, pay for the grid upgrades and power they need, and cover any added emissions so other customers do not carry those costs.
Data centers of 100 megawatts or more will also pay 1 cent per kilowatt-hour into a fund for energy efficiency, home repairs and other help for low-income customers.
Pacific Power serves Albany, Corvallis, Dallas and Independence. Salem's proposed Verrus campus would be served by PGE, which is already under similar rules, and the Salem City Council votes on data center zoning Tuesday.
SALEM, Ore. - Big new data centers that plug into Pacific Power's Oregon grid will have to pay the full cost of the electricity service they need, under rules state regulators approved Friday in Salem.
The Oregon Public Utility Commission adopted a settlement on the utility's large data center tariff in Order No. 26-443, signed Nov. 13 by Commissioners Letha Tawney, Les Perkins and Karin Power. Pacific Power must file final tariff sheets by Nov. 24, and the rules take effect Jan. 1, 2027, according to the order and a Pacific Power news release.
The decision matters in the mid-Willamette Valley, where Pacific Power, a unit of PacifiCorp, serves Albany, Corvallis, Dallas, Independence, Millersburg and surrounding communities. The company said in a 2021 announcement that it had more than 75,000 customers in the mid-valley. It also lands days before the Salem City Council's Tuesday vote on whether the city's zoning allows AI and hyperscale data centers like the one Verrus has proposed at the Mill Creek Corporate Center.
What the new rules require
The rules carry out the POWER Act, House Bill 3546, which the Legislature passed in 2025. The law requires the commission to put data centers that use or can use at least 20 megawatts in their own rate class and to keep the cost of serving them from shifting onto homes and other businesses, the order says.
Under the settlement, which Pacific Power reached with commission staff, the Oregon Citizens' Utility Board and four environmental groups, a new large data center must:
Sign an individual service contract approved by the commission, lasting at least 10 years and no more than 30, with renewals of at least 10 years.
Pay directly for the transmission, distribution and power supply costs of serving it, including studies and the cost of negotiating its contract.
Be served by new resources that are non-emitting. If existing fossil-fuel power serves the facility, the data center is responsible for offsetting the added emissions so Pacific Power's progress toward Oregon's clean energy targets does not slip and other customers do not pay more to comply.
Pay a "community energy benefits" charge of 1 cent per kilowatt-hour if it is 100 megawatts or larger. The money will go to energy efficiency, critical home repairs and small-scale energy projects for low-income Pacific Power customers in Oregon, with rules to be set in a separate case.
The rules also cover existing customers. A data center that signed with Pacific Power before June 16, 2025, falls under the new tariff if serving it requires $10 million or more in new transmission, distribution or generation spending after that date, the order says.
"As Oregon continues to attract investment and economic development, it's important that growth happens in a way that protects affordability for the customers we serve today," Rick Link, Pacific Power's senior vice president of planning and regulation, said in the release.
Why regulators added the 1-cent charge
Commissioners wrote that a load of 100 megawatts or more "places unique burdens on the system" that are hard to measure but real. They pointed to data centers competing with everyone else for scarce clean energy projects, transmission space, transformers and specialized labor. They set the charge to match the one already ordered for Portland General Electric's very large customers, in part to avoid data centers shopping between the two utilities' territories.
The commission also said the approach fits Pacific Power's "rural and dispersed service territory," because it assigns costs to each data center through its own contract.
What opponents said
Not every party agreed. The Data Center Coalition, an industry group, opposed parts of the settlement. It argued that state law requires a stated, cost-of-service rate rather than prices set in individual contracts, that the POWER Act does not let a utility shift its emissions-reduction duties onto a single customer, and that the 1-cent charge should be tied to a set program budget with annual reporting, according to the order.
Amazon Data Services did not oppose the deal but asked for assurance that it would not encourage the utility to overbuild power plants. NewSun asked for changes to how large customers get in line to connect to the grid.
The commission rejected those objections and found the settlement just and reasonable. To address the grid-connection concerns, Pacific Power must share its data center interconnection queue with the commission in a confidential report, publish a public version, and justify any changes. Its first report on the program is due March 31, 2027. Willamette News did not find a public statement from the Data Center Coalition after the order was issued.
What it means for Salem
Most of Salem is served by PGE, and PGE has agreed to supply power to Verrus's proposed Oakline at Mill Creek campus in southeast Salem, the Portland Business Journal reported in October. PGE's large-load rules were set earlier this year in a separate commission case, known as docket UM 2377, and Friday's order notes that several pieces of the Pacific Power deal mirror those decisions.
Verrus has said it would pay the applicable utility rates and the full cost of infrastructure built for its campus, including an on-site substation, Salem Business Journal reported in July.
The Salem City Council meets online at 6 p.m. Tuesday, Nov. 17, to deliberate and vote on whether the city's current code allows AI and hyperscale data centers, as Willamette News reported. A separate public hearing on new city rules for data centers and battery storage is set for Nov. 23.
What happens next
Nov. 24: Pacific Power's deadline to file final tariff sheets that match the order.
Jan. 1, 2027: The new Schedule 401 rules take effect.
March 31, 2027: Pacific Power's first report to the commission is due.
Later: A separate commission case will set rules for how the 1-cent charge money is spent.
KATU and KTVZ also reported on the decision. The full case record is on the commission's UE 463 docket page.
Willamette News Local Desk. Edited by Channing Webb.
Sources
Public Utility Commission of Oregon: Order No. 26-443, docket UE 463, PacifiCorp Schedule 401 (Nov. 13, 2026)
Public Utility Commission of Oregon: docket UE 463 summary and filings
Pacific Power: Pacific Power will require new large data centers to pay their way (Nov. 13, 2026)
Pacific Power: news release on its mid-Willamette Valley service area (Nov. 1, 2021)
Portland Business Journal: PGE reveals $1.7B projects, deal to power controversial Salem data center, by Pete Danko (Oct. 29, 2026)
Salem Business Journal: Salem Data Center: Verrus Shares New Project Details, by Zev Glass (July 17, 2026)
KATU: coverage of the Pacific Power data center decision
KTVZ: New tariff requires Oregon data centers to pay full electricity costs (Nov. 13, 2026)