Salem council's AI data center ruling moves to Nov. 17 as new data center and battery storage rules head to Nov. 23 hearing

Writer: Willamette News Staff
Willamette News Staff
6 days ago
6 min read

Updated: 6 days ago

Rows of black server racks with blue and gray network cables in a brightly lit data center room with a raised tile floor
Server racks inside a data center, 2015. File photo; this is not the facility proposed in Salem. Photo: Carl Lender / Wikimedia Commons, CC BY 2.0

Updated 9:15 p.m. PT Nov. 12: The City of Salem rescheduled Thursday night's special council meeting. Deliberations and a vote on Resolution 2026-46 are now set for 6 p.m. Tuesday, Nov. 17, at Loucks Auditorium. City spokesperson Rob Layne said the delay gives residents time to submit written testimony after the city's Microsoft Outlook email went down; written comments are due by 5 p.m. Friday, Nov. 13, Salem Reporter reported. The Nov. 23 hearing on CA26-04 is unchanged.


Quick Read

  • The Salem City Council's deliberations on Resolution No. 2026-46, which would read the city's zoning code as excluding AI and hyperscale data centers, were moved from Thursday, Nov. 12, to 6 p.m. Tuesday, Nov. 17. The oral hearing is closed, so there is no new spoken testimony.

  • City Attorney Dan Atchison has said the interpretation would apply to Verrus's pending application for an AI data center campus at 4720 Mill Creek Drive SE.

  • A separate city notice sets a Nov. 23 public hearing on case CA26-04, new code amendments that would define data centers and battery energy storage systems, say where they can go and add development standards.

  • Salem's 120-day data center moratorium, adopted Sept. 21, is meant to give the city time to finish those rules. A September staff report said interim amendments were expected by December.


SALEM, Ore. - The Salem City Council will return next Tuesday to the question of whether the city's existing zoning code already shuts out AI and hyperscale data centers, while a second, longer-term set of data center rules is now scheduled for its own public hearing later this month.


Councilors had been set to meet at 6 p.m. Thursday, Nov. 12, in a special meeting to deliberate on Resolution No. 2026-46; that meeting is now Tuesday, Nov. 17, at 6 p.m. The city's meeting calendar lists Loucks Auditorium at the Salem Public Library, 585 Liberty St. SE. The council closed the oral hearing on Nov. 9 after about two and a half hours of testimony and kept the written record open, as Willamette News reported. City Attorney Dan Atchison said then that staff would bring a report summarizing and responding to the written comments, and that councilors could question staff before deciding.


As of Thursday morning, the city's agenda portal showed only an agenda cover for the meeting, and Willamette News was not able to review the staff report before publication.


Two separate tracks

Thursday's decision and the Nov. 23 hearing are different tools that could reach different projects.


Resolution 2026-46 is an interpretation. It asks the council to declare that "data center facilities" in Salem Revised Code 400.110(e), language adopted in 2013 and 2014, does not include AI data centers, hyperscale data centers or other facilities whose defining job is large-scale, continuous computing. Atchison has said that because the council would be clarifying existing code rather than adopting a new standard, the interpretation would apply to Verrus's pending application, the Statesman Journal reported.


The Nov. 23 hearing is on a code amendment. A City of Salem public hearing notice for case CA26-04, published Thursday by Salem Reporter, says the council will consider amendments to the Salem Revised Code on "the regulation of data center facilities and battery energy storage systems (BESS), including how they are defined, where they are allowed, and the establishment of additional development standards applicable to them." The notice does not describe the specific standards being proposed.


New code amendments generally would not govern an application already on file. In July, Salem Planning Administrator Lisa Anderson-Ogilvie told the planning commission that "whatever is in place the day they submit are the regulations we have to evaluate their application against," according to Salem Reporter. That is why Thursday's interpretation, and not the Nov. 23 amendments, is the piece Atchison has tied to the Verrus proposal.


Why battery storage is in the package

Battery energy storage systems are large banks of batteries that store electricity from the grid and release it later. Battery storage was not part of the Sept. 21 moratorium or Resolution 2026-46. The notice does not say why it was added to CA26-04 or whether any battery storage project is proposed in Salem. Willamette News will update this story when the staff report is released.


How the moratorium fits

The council adopted Resolution No. 2026-40, a 120-day moratorium on data centers, on Sept. 21. According to the city attorney's Sept. 21 staff report, it bars the city from accepting, processing or approving land use or building permits for data centers as a primary use, and for accessory data centers with more than 2 megawatts of capacity and a power usage effectiveness above 1.5, including applications filed before the moratorium took effect.


The same report said the city expected "to present interim land use amendments to the City Council by December 2026," and that the council's Data Center Task Force must deliver its final recommendations by December. State law allows a moratorium like Salem's to be extended for up to six months if the council holds a hearing and finds the problem still exists and that reasonable progress is being made, the report said.


Water is central to the city's case. The report said the U.S. Army Corps of Engineers' planned deep drawdowns of Detroit Reservoir are expected to raise turbidity in the North Santiam River, Salem's main drinking water source, and could force the city to stop using the river to protect its slow sand filters. For comparison, it said the State Data Center in Salem peaked at 775 kilowatts of demand this summer and uses about 2,053 gallons of water a day.


What Verrus and its supporters say

Verrus, through its subsidiary Alderstone LLC, has applied to build two single-story buildings totaling about 600,000 square feet, plus a proposed electrical substation, at 4720 Mill Creek Drive SE, according to the Salem Business Journal, citing the city's land use portal. The project has been described as a potential investment of more than $5 billion with about 75 permanent jobs, figures the Business Journal noted are projections.


At the Nov. 9 hearing, according to the city's meeting video, Wendy Kellington, an attorney for Verrus LLC and Alderstone LLC, told the council, "You cannot amend codes by interpretation," and said city planning staff had previously told Verrus in writing that its proposal was a permitted use. Verrus CEO Nelson Abramson said in written testimony that the company is offering a community benefits agreement with $10 million in investment that "would set enforceable caps on water, noise, and power," the Statesman Journal reported. The Salem Chamber's chief executive, speaking for a business coalition, warned that the resolution was a significant departure from current land use practice, and several building trades workers urged a no vote, saying predictable rules matter for family-wage jobs.


Willamette News found no public statement from Verrus on the CA26-04 amendments as of Thursday morning.


How to follow or weigh in

Friday, Nov. 13, 5 p.m.: written testimony deadline on Resolution 2026-46, according to Salem Reporter. Tuesday, Nov. 17, 6 p.m.: council deliberations and vote at Loucks Auditorium, rescheduled from Nov. 12. No new oral testimony. Meetings stream on the CC:Media YouTube channel and Comcast Channel 21.


Monday, Nov. 16, 5 p.m.: the CA26-04 staff report is available from city staff. It posts online at 5 p.m. Thursday, Nov. 19, on the city's council meetings page.


Monday, Nov. 23, 6 p.m.: council public hearing on CA26-04 at Loucks Auditorium. Written testimony is due by 5 p.m. that day to cityrecorder@cityofsalem.net or the City Recorder's Office, 440 Church St. SE, Salem, OR 97301. To testify by Zoom, sign up between 8 a.m. and 3 p.m. that day at cityofsalem.net/comment-at-council. The notice says only people who submit written testimony or testify at the hearing keep the right to appeal the decision.


Questions about the amendments go to Bryce Bishop, Planner III, at 503-540-2399 or PlanningComments@cityofsalem.net, according to the notice.


Willamette News will report the outcome of the council's deliberations. Salem Reporter and the Statesman Journal are also covering the council's data center decisions.


Willamette News Local Desk. Edited by Channing Webb.


Sources

City of Salem: Notice of public hearing, amendments to the Salem Revised Code concerning the regulation of data center facilities and battery energy storage systems, Case No. CA26-04

Salem Reporter: Public notice: Salem City Council public hearing, regulation of data centers (Nov. 12, 2026)

City of Salem: Sept. 21, 2026 special council meeting agenda and staff report, Resolution No. 2026-40 data center moratorium

City of Salem: City Council special meeting, Nov. 12, 2026 (meeting portal)

Salem Reporter: Salem reschedules data center code deliberations and vote to Tuesday (Nov. 12, 2026)

Statesman Journal: Salem delays code change vote that could block Verrus data center (Nov. 10, 2026)

Salem Reporter: CITY MEETING: Data center code interpretation vote postponed to Thursday (Nov. 10, 2026)

Salem Reporter: Planning commission recommends council change code to make data centers conditional (July 29, 2026)

Salem Business Journal: Salem AI data center zoning vote delayed to Nov. 12