State revises Aurora airport plan ahead of Dec. 3 vote, but the Highway 551 move stays


By Willamette News Local Desk. Edited by Channing Webb.
Quick Read
The Oregon Department of Aviation posted an updated Aurora State Airport master plan and revised land use findings on Wednesday, Nov. 25, after working through boundary and zoning issues with Marion County planners.
The plan still calls for moving Highway 551 about 80 feet west and extending the runway 497 feet north to 5,500 feet, but a new line says the department will seek FAA modifications of standards for nonstandard conditions, including the runway object free area, at the project level.
Neighbors, airport businesses and nearby cities have objected, especially to the highway move, which the Statesman Journal reported could remove at least four homes.
The State Aviation Board takes public testimony Dec. 2 from 2 to 3 p.m. and Dec. 3 from 10 a.m. at the ODOT building in Salem, and is scheduled to make a final decision Dec. 3.
SALEM, Ore. (Nov. 26, 2026): A week before a state board is set to vote on it, the Oregon Department of Aviation has reworked parts of its long-range plan for Aurora State Airport in north Marion County. The changes settle a paperwork dispute with Marion County planners, but they leave in place the piece neighbors and many airport users object to most: moving Highway 551.
The department posted the update on its Aurora master plan page on Wednesday, Nov. 25. It includes an updated draft final master plan, amended state agency coordination findings, a new appendix on land use coordination and seven email exchanges with Marion County staff.
What changed
According to the department's update log, the plan now drops the "Draft" label from its cover and layout drawings, adds the FAA's signed conditional approval letter, and adds a map to the airport layout plan showing the airport boundary and nearby zoning as adopted in Marion County's comprehensive plan.
The most notable addition is one sentence in Chapter 5. The log says text was added to the preferred alternative "stating that ODAV will seek project-level MOS for non-standard conditions including the ROFA." An MOS, or modification of standards, is an FAA-approved exception to a design standard. The ROFA, or runway object free area, is the safety zone along the runway that the plan says the highway now sits in.
That matters because airport businesses have argued for months that an MOS could solve the safety-zone problem without moving the road. The update log does not say the highway move has been dropped, and the amended findings still list realigning Highway 551 about 80 feet west to clear the object free area as the plan's first improvement.
Marion County's concerns
Marion County has land use authority over the airport and the land around it. In a Nov. 2 letter, county Planning Director Brandon Reich wrote that the county's earlier comments did not appear to be addressed and asked the state to align the plan with the county's comprehensive plan, including Ordinance No. 1487. That ordinance expanded the airport boundary to include a 16.54-acre private parcel at 22515 Airport Road NE, and the Oregon Land Use Board of Appeals affirmed it on July 29, 2026, the letter says.
The amended findings say department staff met with county staff and the two agreed on a path forward: the state added the new airport boundary and zoning to its layout plan, added Appendix 12, and committed to apply to Marion County to add the master plan to the county's comprehensive plan and to seek conditional use permits for road realignments. The findings note county staff cannot declare the plan compatible with county rules on their own; that decision would come from the county later through that process.
In a Nov. 20 email posted with the update, Reich told state lawyers the revisions "capture our discussion earlier this week very well and provides a path to move forward with county consideration."
Who objects and why
The proposed highway move remains the flash point. The Statesman Journal reported Nov. 25 that neighbors and business owners are united against the plan, including Lori and Don Crouch, who have lived across Highway 551 from the airport since the 1990s. The newspaper reported in October that moving the road could remove at least four homes and that the state spent nearly $1 million in federal money on the plan.
The Aurora Airport Improvement Association, a group of airport businesses and aircraft owners, wrote in its Nov. 3 comments that it supports the runway extension but that the state cannot call a "$50.45 million highway relocation" necessary for safety without fully weighing an MOS, which it says an airport planning expert showed could provide an acceptable level of safety. The group also objected that the plan's capital schedule puts the highway work ahead of the runway extension, which it said the plan estimates at about $23.7 million.
Bruce Bennett, president of Aurora Aviation at the field, wrote in his comment that spending "hundreds of millions of dollars" on the road move would be "absurd" and asked the state to drop plans that reduce ramp space used by businesses including Life Flight Network. The Statesman Journal reported that Life Flight's CEO asked the state in September to postpone a decision because the plan would take about 35 feet of apron in front of its main hangar.
The cities of Aurora and Wilsonville and Clackamas County have also raised concerns, the Statesman Journal reported. The findings summarize Aurora's position that the plan is not compatible with its comprehensive plan and that any expansion should follow annexation and city water and sewer service. The department responded that the city's limits do not border airport property and no direct impact on Aurora is expected.
The state's case
The department says the plan is the result of a four-year process with an advisory committee, surveys and 14 public meetings. In the findings, it says the "single purpose" of moving the highway and Keil Road is to meet FAA safety standards by getting the roads out of the runway object free area.
The FAA's April 6 conditional approval of the airport layout plan lists the 497-foot runway extension as "justified" and shows the Highway 551 realignment. The letter also says approval does not mean federal money will pay for any of it, and that projects still need environmental review and local land use approval before construction.
Department offices were closed for Thanksgiving. The department's position here comes from its published plan documents and findings.
What happens next
The State Aviation Board meets at 10 a.m. Wednesday, Dec. 2, and Thursday, Dec. 3, in the Commission Room of the ODOT T-Building, 355 Capitol St. NE in Salem, and on Microsoft Teams. The Dec. 2 agenda has presentations on the plan and findings, an hour of public testimony from 2 to 3 p.m. and a site visit to the airport. The Dec. 3 agenda continues testimony and lists the board's discussion and "final decision" on the plan.
Written comments closed Nov. 3. Speakers get two minutes each and sign up at the meeting, on a sheet in person or in the Teams chat online, according to the department's testimony notice. Anyone not heard Dec. 2 is automatically moved to Dec. 3.
Even if the board adopts the plan, the highway and road changes would still need Marion County land use approvals, and individual projects would need FAA environmental review and funding, according to the findings and the FAA letter.
Sources
Oregon Department of Aviation, Aurora State Airport Master Plan page, including the Nov. 25, 2026 update and posted public comments.
ODAV, UAO AMP Update Log, Nov. 25, 2026.
ODAV, State Agency Coordination Findings (amended), November 2026.
FAA, Aurora State Airport ALP conditional approval letter, April 6, 2026.
Marion County coordination email, Brandon Reich, Nov. 20, 2026.
Bruce Bennett, Aurora Aviation, public comment, Oct. 30, 2026.
State Aviation Board meetings page, with Dec. 2 and Dec. 3 agendas.
ODAV, "How to Provide Verbal Public Comment at the December State Aviation Board Meetings", Nov. 19, 2026.