Aerial view of Detroit Dam on the North Santiam River with Detroit Lake behind it, surrounded by forested hills, as Oregon Route 22 winds along the shore
Detroit Dam and Detroit Lake on the North Santiam River near Detroit, seen from the air in 1990. File photo. Photo: Bob Heims, U.S. Army Corps of Engineers / Wikimedia Commons, public domain

Willamette News Local Desk. Edited by Channing Webb.


Quick Read

  • A three-judge panel of the U.S. Court of Appeals for the Ninth Circuit on Friday, Nov. 20, denied emergency requests from Marion County, Stayton and Salem to stop the Army Corps of Engineers' deep drawdown of Detroit Lake while their appeals proceed.

  • The Corps plans to lower the reservoir 25 feet below its normal winter level of 1,450 feet, to 1,425 feet, hold it there about two weeks and then refill it.

  • The Corps said Friday that reports of a start this weekend are not accurate and that it will announce when the drawdown begins, reaches its target, ends and refills, the Statesman Journal reported.

  • Salem says sediment from the drawdown could force it to stop treating North Santiam River water for a time. The City Council votes Monday, Nov. 23, on extending its drawdown emergency declaration.


SALEM, Ore. - A federal appeals court on Friday turned down a last-ditch request from Salem and Marion County to stop the U.S. Army Corps of Engineers from drawing down Detroit Lake, clearing the way for the deep drawdown to go ahead in the coming weeks.


In a one-paragraph order entered at 3:29 p.m. Friday, a Ninth Circuit panel of Circuit Judges Tallman, Johnstone and Tung denied the emergency motions for injunctive relief filed by Marion County and the City of Stayton in one appeal and by the City of Salem in the other, according to the court docket. The order cites the legal standard for preliminary injunctions and gives no further explanation. It also sets a schedule for the appeals to continue: opening briefs are due Dec. 3, and the government's answering briefs are due Dec. 31.


It is the third time this month a court has declined to block the operation. U.S. District Judge Mustafa T. Kasubhai in Eugene denied the city's and county's requests for a preliminary injunction on Nov. 4, as Willamette News reported, and on Nov. 18 he denied their emergency motion for an injunction while the appeal is heard, writing that they had failed "to make a clear showing that irreparable harm is likely," according to the district court docket.


The Statesman Journal reported the ruling Friday and said the lawsuit now returns to district court for a potential trial at a later date.


When the drawdown starts

The Corps has not announced a start date. It will lower the reservoir below its normal winter level of 1,450 feet above sea level sometime in late November or early December, until it reaches 1,425 feet, then hold it there for two weeks before refilling, the Statesman Journal reported.


The Corps said reports that the drawdown will begin this weekend are not accurate, according to the Statesman Journal. "We will be keeping the public informed every step of the way," the Corps said in a statement Friday, adding that it will tell the public "when we start the drawdown, when we reach the target depth, when the deep drawdown is complete and when we refill to the normal winter reservoir level."


Those weekend reports traced to a Corps court filing. OPB and KATU reported this week that a Corps notice filed in district court on Nov. 17 said the drawdown "may" start as soon as 9 a.m. Saturday, Nov. 21. At the Corps' online public session on Nov. 18, program manager Kathryn Tackley said a Saturday start "is not the case" and that the drawdown would be timed to a dry stretch of weather, according to Santiam Silt, a volunteer river-monitoring project that attended and recorded the session.


In its Nov. 5 release, the Corps said reaching 1,425 feet may take up to two weeks and the lake would then be held there for two weeks unless a storm requires refilling sooner. The Corps said the reservoir reached 1,425 feet in 2015 and 2019 "with no adverse turbidity conditions reported downstream" and that drinking water "is not expected to be impacted." It plans to step the lake lower in later years, to an eventual fall target of 1,395 feet, to help young salmon and steelhead reach the dam's lower outlets, as called for in a 2024 federal biological opinion under the Endangered Species Act.


Detroit Lake stood at about 1,458.7 feet at 6 p.m. Friday, according to Army Corps reservoir data, still above the 1,450-foot normal winter level. The deep drawdown is the 25 feet below that level, according to the Corps' Nov. 5 release.


What it means for Salem's water

Marion County, Salem and Stayton sued the Corps in July, OPB reported. The city and county argue the drawdown could flush sediment into the North Santiam River and clog drinking water intakes, which could affect water for 220,000 people in the Salem and Stayton area, according to the Statesman Journal. In their Nov. 17 appeal, Marion County and Stayton said the operation would "endanger clean drinking water for hundreds of thousands of Marion County residents," according to OPB.


Salem treats its water at Geren Island near Stayton, about 27 miles downstream of Detroit Dam, using slow sand filters that clog when the river turns muddy, the city says on its drawdown page. If river water cannot be treated, the city plans to use groundwater wells on Geren Island, its Aquifer Storage and Recovery system in south Salem and an emergency connection to Keizer's well system. The city says those sources together cannot yet meet daily demand of about 24 to 25 million gallons, and that during the drawdown it may ask residents to use less water.


The Corps says state agencies, the Corps and local water providers have an emergency response plan with steps to modify, pause or stop the drawdown if a drinking water emergency develops, according to its Nov. 5 release. The Oregon Health Authority told KATU that Gov. Tina Kotek's office could order a pause if water quality problems arise.


Salem leaders declined to comment on the appeals court decision because the case is ongoing, the Statesman Journal reported. Willamette News found no new City of Salem statement or water advisory on the ruling as of Friday evening; the city's most recent drawdown release, on Nov. 5, announced its appeal. The city posts updates at cityofsalem.net/drawdown, and its Water Quality Hotline is 503-588-6323.


What's next

The Salem City Council on Monday, Nov. 23, will consider a resolution extending its emergency declaration for the drawdown, which expires Dec. 31, and will hear a staff update on the drawdown and the city's water resiliency work, according to the council agenda. The council first approved the declaration in July 2025 to speed up work on new wells, a pump station for the Keizer connection and re-sanding of the Geren Island filters, the city says.


Willamette News will report when the Corps announces the start of the drawdown and will follow river turbidity and Salem's water supply.


Sources

U.S. Court of Appeals for the Ninth Circuit: Order denying motions for injunctive relief, Nos. 26-7415 and 26-7451 (Nov. 20, 2026), docket via CourtListener

U.S. Court of Appeals for the Ninth Circuit: City of Salem appeal docket, No. 26-7451, via CourtListener

U.S. District Court for the District of Oregon: Marion County v. U.S. Army Corps of Engineers, 6:26-cv-00956, docket via CourtListener (Nov. 18 order)

Statesman Journal: Final request to halt Detroit Lake drawdown denied by appeals court, by Zach Urness (Nov. 20, 2026)

U.S. Army Corps of Engineers Portland District: Detroit deep drawdown to proceed; here's what you need to know (Nov. 5, 2026)

OPB: Army Corps could begin Detroit Lake drawdown this weekend, by Joni Auden Land (Nov. 18, 2026)

KATU: Detroit reservoir drawdown could start Saturday as governments urge court to stop it, by Barry Mangold (Nov. 17, 2026)

City of Salem: Detroit Lake Deep Drawdown page and FAQ

City of Salem via FlashAlert: City of Salem preparing to appeal a U.S. District Court decision (Nov. 5, 2026)

City of Salem: City Council agenda, Nov. 23, 2026, items 3.2.2 and 6.5

U.S. Army Corps of Engineers: Detroit Reservoir forebay elevation, CWMS data (accessed Nov. 20, 2026)

Santiam Silt: Detroit Lake drawdown news and events (reviewed Nov. 20, 2026)